Reconstruction & Widening of Soldiers Home Road, from Sagamore Parkway to Kalberer Road

Updated 03/04/2026: Design changes for Phase 1 and Phase 2 are in progress, including enhanced pedestrian safety features and a confirmed roundabout at Kalberer Road. See details below.

Phasing, Design Details, and Public Involvement Timeline

WEST LAFAYETTE, Ind. – The Soldiers Home Road Reconstruction project continues to progress through planning and design milestones. The update below includes newly defined construction phasing, design features, right-of-way impacts, and upcoming opportunities for public input.

Current Project Scope and Design Features

The project will reconstruct Soldiers Home Road in two phases:

  • Phase I: Sagamore Parkway to Hamilton Street
  • Phase II: Hamilton Street to Kalberer Road

View Overview Phase 1 Map – Updated March 2026

View Overview Phase 2 Map

View Overview Phase 2 Updated Map – Preliminary Preferred Alternatives

Roadway Design & Improvements

The proposed roadway improvements include:

  • One 11-foot travel lane in each direction
  • A 12-foot center two-way left-turn lane
  • A 10-foot multi-use trail
  • A 5-foot sidewalk
  • 5-foot landscaped buffers
  • Curb and gutter
  • New pavement and street lighting
  • A closed storm drainage system

View Typical Section

Additional Improvements:

Intersection Upgrades:

  • Reconstruct Sagamore Parkway ramp intersection as a roundabout
  • Evaluate potential roundabout at Kalberer Road
  • Retain other intersections as conventional unsignalized

Driveways and Accessibility:

  • Replacement of driveway approaches within the right-of-way
  • ADA-compliant curb ramps at intersections
  • Trail and sidewalk connections to existing infrastructure

Design Changes (March 2026 Update)

Engineering refinements are currently underway for both phases. These adjustments reflect continued technical review and community input, with a focus on safety and long-term functionality.

Phase 1 – Design Changes in Progress

Raised Intersection – Cumberland Avenue

A raised intersection has been incorporated at Cumberland Avenue as a traffic-calming measure to reduce vehicle speeds along Soldiers Home Road.

Multi-Use Trail Relocation

The multi-use trail has been relocated entirely to the west side of Soldiers Home Road to eliminate mid-corridor crossings and enhance pedestrian and cyclist safety. A sidewalk will remain on the east side.

Enhanced Crosswalks

Crosswalks are now planned at:

  • Sagamore Parkway Roundabout
  • Cumberland Avenue
  • Hamilton Street

A third crosswalk has been added at Cumberland Avenue.
All crosswalks will include:

  • Flashing pedestrian beacons
  • Pedestrian warning signage

These improvements enhance visibility and increase driver awareness.

Bus Stop Safety Improvement

A concrete center median will be added at the bus stop in front of University Crossing Apartments (2501 Soldiers Home Road) to improve pedestrian safety and traffic flow.

Stormwater Improvements

Stormwater detention features have been added to mitigate downstream impacts and improve drainage performance.

Phase 2 – Design Changes in Progress

Kalberer Road Roundabout

The intersection at Kalberer Road will be constructed as a roundabout to improve traffic flow and enhance safety.

Anticipated Right-of-Way Needs

Permanent and/or temporary right-of-way will be needed on each side of the roadway to accommodate the improvements. Acquisition needs will vary by property but generally range from 5 to 10 feet.

Approximately 75 parcels will be impacted across both phases.

Traffic Maintenance During Construction

Soldiers Home Road will be closed to through-traffic during construction. Key details:

  • Official detour routes will be established
  • Each phase will include sub-phases to improve local access and reduce detour times
  • Street and driveway connections with a single outlet will be constructed in halves to maintain access

Funding

This project utilizes federal funding with a required local funding match.

Updated Project Schedule

(All dates are subject to funding availability and environmental approvals.)

ActivityPhase IPhase II
Begin Right-of-Way AcquisitionFall 2025Late 2027
Begin Utility RelocationSpring 2027Late 2028
Begin ConstructionSpring 2028Late 2029 – Early 2030
Construction DurationOne YearOne Year

Public Involvement Opportunities

  • Initial Public Input Sessions (Phases 1 & 2): Held in April 2023 and January 2024
  • Public Hearing (Environmental Document), Phase 1: Held in August 2025
  • Third Design Input Session (Phases 1 & 2): Mid/Late 2027
  • Opportunity to Request Public Hearing (Environmental Document), Phase 2: Mid-2027
  • Phase 2 Design Input Session: Mid-2028

Public Hearing Documents

For questions or feedback, contact:

  • City of West Lafayette Engineering Department – engineering@westlafayette.in.gov or 765.807.8980
  • VS Engineering – clem@vsengineering.com or 765.705.0412

Send Feedback

Fill in the form below and our team will be happy to assist you

Call

(765) 775-5160

Email

development@westlafayette.in.gov