Approved
Foundation – Ancillary Buildings
Last Updated: April 13, 2026The foundation permits for 14 ancillary buildings have been approved. These ancillary buildings include guard houses, pump houses, warehouses, and storage facilities. What this means:These approvals authorize SK hynix to...
Temporary Power Phase 1
Last Updated: April 2, 2026The permit for Temporary Power – Phase 1 has been approved. What this means:This approval authorizes the initial installation of temporary electrical infrastructure to bring power from the utility provider...
Final Site and Paving Plans
Last Updated: February 6, 2026SK hynix received approval of its final site layout and paving plans. This approval confirms that the project’s proposed stormwater and drainage design meets County requirements. It is an essential...
Foundation
Last Updated: January 15, 2026The foundation permits for the Office, Fab, and Central Utility Building (CUB) structures have been approved. What this means:These approvals authorize SK hynix to begin work on the footings and...
Mass Grading
Last Updated: July 29, 2025The City has reviewed the preliminary drainage calculations and mass grading plan for Project Neuron (SK SITE). Based on the information submitted, the City will be issuing a permit to begin grading and site preparation for this project once the conditions of the permit are met. Residents should begin to see construction entrances and erosion control measures being installed. Following that work, the grading contractor will begin excavating the detention ponds and grading the site for the initial phase of construction. Before any building permits are issued, the company will be submitting a full set of construction plans and details to the city for further review.