Cherry Lane
Realignment Project

Detail2

Duration

November 2022 – September 2023

Categories

About

Cherry Lane will be realigned to accommodate Purdue University’s new Pete Dye Clubhouse. With this project, the area will also be enhanced with a new roundabout, multi-use trail, more lighting, and new stormwater infrastructure. Cherry Road closure will begin in March 2023 between Northwestern Avenue and McCormick Road with the project expected to wrap up by September 2023.

Next Moves

Cherry Lane is now open from McCormick Road to Northwestern Avenue. Construction of the Pete Dye Clubhouse will continue into 2024.

Due to rising construction costs, the Cherry Lane multi-trail connecting Northwestern Avenue to McCormick Road is being postponed. The City of West Lafayette will re-bid the project to be constructed in 2024.

Why This Project?

WL Icons-02

Better Connectivity

Provide multimodal connections to:

WL Icons-03

Pedestrian Safety

Promote safe travel while:

WL Icons-04

Trails & Greenspace Use

Make use of the city’s investments in:

Closure Map

Project Updates

WEST LAFAYETTE, Ind. – The Cherry Lane Multi-Use Trail project is scheduled to be completed and opened at the end of August …

Stay In-the-Know

Receive project announcements and direct updates about closures, detours and more through text and email alerts.

Detail2

Send Feedback

Fill in the form below and our team will be happy to assist you

Call

(765) 775-5160